New projects in Bengaluru Rural
Every project in Bengaluru Rural that files its sales and construction with Karnataka RERA, as filed.
Brokers: this week’s stock sheet for Bengaluru Rural →Booked so far
30063 of 56618
Across 223 projects, at each one's latest filing.
Booked in Q2 2026-27
1
By the 5 projects that filed both of the last two quarters; 4 of them booked none.
Devanahalli · 103 projects
- Barca At Godrej MSR City
M S RAMAIAH VENTURES LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
57 of 57 homes booked · 19% built · 30% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030
- Barca II At Godrej MSR City
M S RAMAIAH VENTURES LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
593 of 602 homes booked · 16% built · 23% of the promised time used · Q2 2026-27 filing · completion promised 31 Dec 2030
- Def Col-Peace Haven
ORGANIZE INDIA REAL ESTATE DEVELOPMENTS LLP · Devanahalli, Bengaluru Rural · Plotted Development
0 of 52 plots booked · 75% developed · 50% of the promised time used · Q2 2026-27 filing · completion promised 23 Jun 2027
- Greybrick -Talking to the Clouds
GREYBRICK PROJECTS LLP · Devanahalli, Bengaluru Rural · Plotted Development
0 of 31 plots booked · 60% developed · 12% of the promised time used · Q2 2026-27 filing · completion promised 20 Apr 2029
- Highgrove
SAMANVI ESTATES LLP · Devanahalli, Bengaluru Rural · Plotted Development
5 of 153 plots booked · 80% developed · 5% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2028
- Hillcrest Haven
M/s Chhabindra Kumar Pradhan · Devanahalli, Bengaluru Rural · Plotted Development
0 of 38 plots booked · 80% developed · 34% of the promised time used · Q2 2026-27 filing · completion promised 30 May 2028
- Aarohana Adira
AAROHANA PROJECTS · Devanahalli, Bengaluru Rural · Residential/Group Housing
0 of 140 homes booked · 4% built · 0% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Abhi Homes
ABHI DEVELOPERS · Devanahalli, Bengaluru Rural · Residential/Group Housing
9 of 292 homes booked · 68% built · 93% of the promised time used · Q1 2026-27 filing · completion promised 30 Dec 2026
- Aeropolis, a project of Sattva Group
TRINAYANI REALTOR PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
938 of 1001 homes booked · 89% built · 99% of the promised time used · Q1 2026-27 filing · completion promised 9 Jul 2026
- Arvind Orchards
Arvind Smart Homes Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
264 of 313 plots booked · 100% developed · 41% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Arvind Orchards Phase-2
Arvind Smarthomes Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
20 of 70 plots booked · 80% developed · 12% of the promised time used · Q1 2026-27 filing · completion promised 29 Dec 2029
- Arvind The Park
Arvind Homes Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
256 of 340 plots booked · 84% developed · 27% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Assetz City of Palms
ASSETZ INVESTMENTS AND HOLDINGS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
0 of 620 plots booked · 84% developed · 0% of the promised time used · Q1 2026-27 filing · completion promised 15 Feb 2029
- Aurum at Brigade El Dorado
Brigade Tetrarch Private Limited · Devanahalli, Bengaluru Rural · Residential/Group Housing
477 of 477 homes booked · 81% built · 67% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Aurum Valley
BANGARUKADIYALA SYED MUNAF · Devanahalli, Bengaluru Rural · Plotted Development
43 of 43 plots booked · 100% developed · 48% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Birla Trimaya Phase-2
BIRLA ARNAA LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
470 of 473 homes booked · 19% built · 38% of the promised time used · Q1 2026-27 filing · completion promised 20 Jun 2029
- Birla Trimaya Phase-3
BIRLA ARNAA LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
439 of 463 homes booked · 4% built · 25% of the promised time used · Q1 2026-27 filing · completion promised 31 Aug 2030
- Birla Trimaya Phase-4
Birla Arnaa LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
447 of 518 homes booked · 2% built · 7% of the promised time used · Q1 2026-27 filing · completion promised 15 Dec 2031
- Birla Trimaya-Phase-I
BIRLA ARNAA LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
555 of 556 homes booked · 63% built · 55% of the promised time used · Q1 2026-27 filing · completion promised 31 Oct 2028
- Brigade Oasis - Phase 1
Brigade Enterprises Ltd · Devanahalli, Bengaluru Rural · Plotted Development
306 of 307 plots booked · 100% developed · 100% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2026
- Brigade Oasis - Phase 2
Brigade Enterprises Ltd · Devanahalli, Bengaluru Rural · Plotted Development
216 of 221 plots booked · 100% developed · 100% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2026
- Brigade Oasis - Phase 3
Brigade Enterprises Ltd · Devanahalli, Bengaluru Rural · Plotted Development
443 of 460 plots booked · 100% developed · 100% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2026
- Brush Strokes BY MH
MH Properties · Devanahalli, Bengaluru Rural · Plotted Development
0 of 81 plots booked · 8% developed · 17% of the promised time used · Q1 2026-27 filing · completion promised 28 Jan 2029
- Century Trails Phase 2
Century Trails LLP · Devanahalli, Bengaluru Rural · Plotted Development
28 of 49 plots booked · 100% developed · 35% of the promised time used · Q1 2026-27 filing · completion promised 31 May 2028
- Classic Merusri Canaan Phase - II
MERUSRI DEVELOPERS · Devanahalli, Bengaluru Rural · Plotted Development
0 of 66 plots booked · 62% developed · 11% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- DNR Solace
DNR Corporation Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
0 of 432 plots booked · 97% developed · 82% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Earthsong BY Manyata Phase-5a
Manyata Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Plotted Development
216 of 216 plots booked · 68% developed · 68% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Earthsong BY Manyata Phase-5B
Manyata Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Plotted Development
154 of 154 plots booked · 59% developed · 68% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Ebony at Brigade Orchards
BCV Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Residential/Group Housing
206 of 232 homes booked · 36% built · 33% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2029
- Embassy Greenshore
EMBASSY DEVELOPMENTS LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
621 of 878 homes booked · 10% built · 10% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2031
- Embassy Paradiso
EMBASSY DEVELOPMENTS LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
0 of 48 plots booked · 95% developed · 45% of the promised time used · Q1 2026-27 filing · completion promised 31 Aug 2027
- Embassy Springs - Phase 2a, Apartments
EMBASSY DEVELOPMENTS LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
673 of 826 homes booked · 72% built · 84% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Embassy Verde
EMBASSY DEVELOPMENTS LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
1034 of 1044 homes booked · 20% built · 26% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Fairmont at Brigade Orchards
BCV Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Residential/Group Housing
92 of 92 homes booked · 99% built · 63% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Fortius Good Earth
RS-GK REAL ESTATES LLP · Devanahalli, Bengaluru Rural · Plotted Development
19 of 63 plots booked · 30% developed · 30% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Heritage Enclave
IG3 Infra Limited · Devanahalli, Bengaluru Rural · Plotted Development
0 of 118 plots booked · 16% developed · 2% of the promised time used · Q1 2026-27 filing · completion promised 15 Dec 2029
- Hydenben Clifton
HYDENBEN DEVELOPERS LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
35 of 98 homes booked · 27% built · 39% of the promised time used · Q1 2026-27 filing · completion promised 2 Apr 2028
- Impact Sanvi Aero Gardens
SANVI CONSTRUCTIONS · Devanahalli, Bengaluru Rural · Residential/Group Housing
62 of 316 homes booked · 41% built · 37% of the promised time used · Q1 2026-27 filing · completion promised 30 Dec 2028
- Ivc Northshire Address
Indiabuild Realty Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
59 of 105 plots booked · 85% developed · 41% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Ivory Phase 1 at Brigade Orchards
BCV Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Residential/Group Housing
454 of 457 homes booked · 100% built · 90% of the promised time used · Q1 2026-27 filing · completion promised 30 Dec 2026
- Ivory Phase 2 At Brigade Orchards
BCV Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Residential/Group Housing
487 of 487 homes booked · 83% built · 63% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Konig North County
Konig Homes · Devanahalli, Bengaluru Rural · Plotted Development
0 of 99 plots booked · 78% developed · 52% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Konig Pearl County 1
Konig Homes · Devanahalli, Bengaluru Rural · Plotted Development
0 of 74 plots booked · 55% developed · 20% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Konig Pearl County 2
Konig Homes · Devanahalli, Bengaluru Rural · Plotted Development
0 of 136 plots booked · 55% developed · 20% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Kumar Palazzio
Kumar Vista Properties LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
2 of 29 homes booked · 6% built · 13% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2030
- Laurel & Maple at Brigade Orchards
BCV Developers Pvt Ltd · Devanahalli, Bengaluru Rural · Residential/Group Housing
81 of 311 homes booked · 13% built · 8% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2030
- Legacy Mihira
LEGACY GLOBAL PROJECTS PVT LTD · Devanahalli, Bengaluru Rural · Plotted Development
13 of 279 plots booked · 10% developed · 17% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Madhuban
SIDHARTH MADHUBAN · Devanahalli, Bengaluru Rural · Plotted Development
26 of 128 plots booked · 95% developed · 47% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2028
- Merusri Sienna 1
Merusri Sienna Developers Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
0 of 107 plots booked · 0% developed · 4% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2031
- Merusri Sienna II
Merusri Estate Holdings Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
0 of 113 plots booked · 0% developed · 0% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2031
- Merusri Sunscape
MERUSRI SUNSCAPE LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
14 of 76 homes booked · 15% built · 21% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2030
- Merusri Swamy Orchards
MERUSRI DEVELOPERS · Devanahalli, Bengaluru Rural · Plotted Development
0 of 119 plots booked · 89% developed · 33% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2030
- MVN Aero One T5 & T6
MF FARMLANDS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
107 of 137 homes booked · 95% built · 71% of the promised time used · Q1 2026-27 filing · completion promised 20 Jul 2027
- MVN Aero One Tower 4
MF FARMLANDS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
49 of 54 homes booked · 99% built · 85% of the promised time used · Q1 2026-27 filing · completion promised 20 Dec 2026
- Natures Sign BY Shreyas
SHREYAS INFRA PROJECTS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
1 of 124 plots booked · 10% developed · 25% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2028
- Park Cubix Phase 2
Sattva Resi Private Limited · Devanahalli, Bengaluru Rural · Residential/Group Housing
481 of 798 homes booked · 40% built · 29% of the promised time used · Q1 2026-27 filing · completion promised 15 Sept 2029
- Prakriti Meadows
MSR DEVELOPRS · Devanahalli, Bengaluru Rural · Plotted Development
0 of 99 plots booked · 55% developed · 11% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Prestige Autumn Leaves
PRESTIGE ESTATES PROJECTS LTD · Devanahalli, Bengaluru Rural · Plotted Development
208 of 240 plots booked · 42% developed · 50% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2027
- Prestige Crystal Lawns
PRESTIGE ESTATES PROJECTS LTD · Devanahalli, Bengaluru Rural · Plotted Development
190 of 235 plots booked · 38% developed · 50% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2027
- Prestige Gardenia Estate
PRESTIGE ESTATES PROJECTS LTD · Devanahalli, Bengaluru Rural · Plotted Development
516 of 516 plots booked · 66% developed · 57% of the promised time used · Q1 2026-27 filing · completion promised 30 Apr 2027
- Prestige Gardenia Estate Phase 2
PRESTIGE ESTATES PROJECTS LTD · Devanahalli, Bengaluru Rural · Plotted Development
0 of 195 plots booked · 1% developed · 4% of the promised time used · Q1 2026-27 filing · completion promised 31 Oct 2027
- Prestige Greenbrook
PRESTIGE ESTATES PROJECTS LTD · Devanahalli, Bengaluru Rural · Plotted Development
254 of 324 plots booked · 26% developed · 50% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2027
- Prestige Marigold Phase II
ACE REALTY VENTURES · Devanahalli, Bengaluru Rural · Plotted Development
523 of 717 plots booked · 64% developed · 27% of the promised time used · Q1 2026-27 filing · completion promised 30 Nov 2027
- Prestige Sanctuary
VILLAGE DE NANDI PVT LTD · Devanahalli, Bengaluru Rural · Residential/Group Housing
85 of 85 homes booked · 100% built · 100% of the promised time used · Q1 2026-27 filing · completion promised 31 May 2026
- Raagam Phase-1
ONE BANGALORE LUXURY PROJECTS LLP · Devanahalli, Bengaluru Rural · Plotted Development
0 of 576 plots booked · 94% developed · 83% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Raagam Phase-II
ONE BANGALORE LUXURY PROJECTS LLP · Devanahalli, Bengaluru Rural · Plotted Development
0 of 7 plots booked · 20% developed · 47% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2028
- Sattva Aeropolis Phase 2
TRINAYANI REALTORS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
329 of 554 homes booked · 33% built · 25% of the promised time used · Q1 2026-27 filing · completion promised 16 Oct 2028
- Sattva Bhumi
SHIRASA CONSTRUCTION PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
332 of 343 plots booked · 100% developed · 77% of the promised time used · Q1 2026-27 filing · completion promised 30 Dec 2026
- Sattva Vasanta Cove
Sattva Resi Private Limited · Devanahalli, Bengaluru Rural · Residential/Group Housing
71 of 200 homes booked · 9% built · 11% of the promised time used · Q1 2026-27 filing · completion promised 27 Dec 2030
- Sattva Vasanta Skye
Sattva Resi Private Limited · Devanahalli, Bengaluru Rural · Residential/Group Housing
21 of 56 homes booked · 14% built · 19% of the promised time used · Q1 2026-27 filing · completion promised 6 May 2031
- Shantivan
SIDHARTH MADHUBAN · Devanahalli, Bengaluru Rural · Plotted Development
0 of 80 plots booked · 35% developed · 29% of the promised time used · Q1 2026-27 filing · completion promised 31 Oct 2028
- Sobha Oakshire Phase 1 Wing 1,2,7 and 8
SOBHA LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
30 of 30 homes booked · 100% built · 87% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Sobha Oakshire Phase 2 Wing 3,4,9 and 10
SOBHA LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
30 of 30 homes booked · 90% built · 77% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2027
- Sobha Oakshire Phase 3 Wing 5,6,11 and 12
SOBHA LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
20 of 20 homes booked · 90% built · 68% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Sumadhura Panorama Phase-I
SUMADHURA REALTY · Devanahalli, Bengaluru Rural · Plotted Development
414 of 539 plots booked · 90% developed · 49% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Sumadhura Panorama Phase-II
SUMADHUARA EMPIRE ESTATES PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
0 of 443 plots booked · 59% developed · 3% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Summer Skies
Reddy Veeranna Construction Private Limited · Devanahalli, Bengaluru Rural · Plotted Development
1 of 117 plots booked · 30% developed · 6% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Summers At Orchid Nirvana
MANGO DEVELOPERS · Devanahalli, Bengaluru Rural · Plotted Development
504 of 504 plots booked · 10% developed · 5% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2031
- Surya Serene Skyline
Surya Serene Skyline · Devanahalli, Bengaluru Rural · Residential/Group Housing
17 of 117 homes booked · 43% built · 31% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Tangled Up In Green
TANGLED UP IN GREEN PROPERTIES PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
972 of 972 plots booked · 38% developed · 50% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- The Landmark
KADIRI VENKATA NARASIMHA REDDY · Devanahalli, Bengaluru Rural · Plotted Development
0 of 99 plots booked · 20% developed · 5% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2031
- The Midsummer Rain-Villa Plot Development Phase 4
AXIS CAPSTONE REALTY LLP · Devanahalli, Bengaluru Rural · Plotted Development
0 of 28 plots booked · 3% developed · 28% of the promised time used · Q1 2026-27 filing · completion promised 30 Apr 2029
- The Roots
SRK INFRA PROJECTS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Residential/Group Housing
28 of 100 homes booked · 24% built · 16% of the promised time used · Q1 2026-27 filing · completion promised 30 Jul 2030
- The Secret Lake
EQUINOX GLOBAL SHELTERS · Devanahalli, Bengaluru Rural · Plotted Development
431 of 701 plots booked · 68% developed · 25% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2030
- Vaishnavi At-One Life IV
VAISHNAVI AT-ONE LIFE PARK LLP and AT-ONE ESTATES PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
2 of 227 plots booked · 65% developed · 8% of the promised time used · Q1 2026-27 filing · completion promised 18 Dec 2027
- Varnam Phase 1a
ONE BANGALORE LUXURY PROJECTS LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
48 of 48 homes booked · 10% built · 17% of the promised time used · Q1 2026-27 filing · completion promised 31 Aug 2030
- Varnam Phase 1B
ONE BANGALORE LUXURY PROJECTS LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
249 of 285 homes booked · 9% built · 17% of the promised time used · Q1 2026-27 filing · completion promised 31 Aug 2030
- Varnam Phase 1C
ONE BANGALORE LUXURY PROJECTS LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
262 of 298 homes booked · 9% built · 16% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2031
- Varnam Phase 1D
ONE BANGALORE LUXURY PROJECTS LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
135 of 211 homes booked · 7% built · 9% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2031
- White Lotus Amanvana
WHITE LOTUS ALLIED HOMES LLP · Devanahalli, Bengaluru Rural · Residential/Group Housing
10 of 95 homes booked · 15% built · 16% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Provident Deansgate
Puravankara Limited · Devanahalli, Bengaluru Rural · Residential/Group Housing
130 of 147 homes booked · 76% built · 67% of the promised time used · Q4 2025-26 filing · completion promised 31 May 2027
- Provident Deansgate Phase 2
Puravankara Limited · Devanahalli, Bengaluru Rural · Residential/Group Housing
84 of 141 homes booked · 24% built · 34% of the promised time used · Q4 2025-26 filing · completion promised 31 Mar 2028
- Signature One
THEME AMBIENCE ROI PROJECTS PRIVATE LIMITED · Devanahalli, Bengaluru Rural · Plotted Development
21 of 129 plots booked · 100% developed · 33% of the promised time used · Q4 2025-26 filing · completion promised 31 Mar 2030
- Swaram Phase-2
One Bangalore Luxury Projects LLP · Devanahalli, Bengaluru Rural · Plotted Development
23 of 23 plots booked · 100% developed · 100% of the promised time used · Q4 2025-26 filing · completion promised 31 Mar 2026
- The Midsummer Rain-Villa Plot Development Phase 3
AXIS CAPSTONE REALTY LLP · Devanahalli, Bengaluru Rural · Plotted Development
0 of 43 plots booked · 100% developed · 43% of the promised time used · Q4 2025-26 filing · completion promised 30 Apr 2028
- Earth Aroma Phase-2
Parisara Builders and Developers · Devanahalli, Bengaluru Rural · Plotted Development
78 of 78 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Earthsong BY Manyata Phase-5C
Square plots Private limited · Devanahalli, Bengaluru Rural · Plotted Development
57 of 62 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Elite Park Phase 4
Elite Estates · Devanahalli, Bengaluru Rural · Plotted Development
0 of 105 plots booked · 100% developed · 18% of the promised time used · Q3 2025-26 filing · completion promised 2 May 2026
- Elite Rose Phase 2
Elite Estates · Devanahalli, Bengaluru Rural · Plotted Development
0 of 70 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Elite Rose Phase 3
Elite Estates · Devanahalli, Bengaluru Rural · Plotted Development
0 of 35 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Northern Boulevard
Nimishamba Developers · Devanahalli, Bengaluru Rural · Plotted Development
78 of 269 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Pearl at Brigade Atmosphere
Brigade Enterprises Ltd · Devanahalli, Bengaluru Rural · Residential/Group Housing
132 of 132 homes booked · 100% built · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Rare Earth Athena
Rarearth Athena · Devanahalli, Bengaluru Rural · Plotted Development
7 of 80 plots booked · 80% developed · 3% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2026
Hosakote · 92 projects
- SLN Nidhi Aura
SLN INFRA · Hosakote, Bengaluru Rural · Plotted Development
0 of 88 plots booked · 80% developed · 48% of the promised time used · Q2 2026-27 filing · completion promised 31 Dec 2027
- 96 Brick wood Avenue
Cinoti ventures LLP · Hosakote, Bengaluru Rural · Residential/Group Housing
0 of 48 homes booked · 8% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 16 May 2031
- Aakriti Emerald
AAKRITI PROJECTS · Hosakote, Bengaluru Rural · Residential/Group Housing
27 of 130 homes booked · 33% built · 27% of the promised time used · Q1 2026-27 filing · completion promised 31 Aug 2028
- Adarsh Paradise
A1 BUILDERS · Hosakote, Bengaluru Rural · Residential/Group Housing
85 of 238 homes booked · 87% built · 85% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Adithya Paradise -5
PARADISE HOMES · Hosakote, Bengaluru Rural · Plotted Development
61 of 156 plots booked · 100% developed · 50% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2027
- Agm Builders
AGM BUILDERS · Hosakote, Bengaluru Rural · Plotted Development
0 of 28 plots booked · 100% developed · 14% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Alcor
NAGARJUNA STRUCTURAL CORPORATION PRIVATE LIMITED · Hosakote, Bengaluru Rural · Plotted Development
0 of 71 plots booked · 50% developed · 5% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Anahata
ISHTIKA VIBRANIUM DEVELOPERS LLP · Hosakote, Bengaluru Rural · Residential/Group Housing
118 of 259 homes booked · 30% built · 30% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2029
- Anahata Phase - 2
ISHTIKA VIBRANIUM DEVELOPERS LLP · Hosakote, Bengaluru Rural · Residential/Group Housing
82 of 181 homes booked · 20% built · 24% of the promised time used · Q1 2026-27 filing · completion promised 31 Jul 2029
- Anthill Silverfields
Anthill Projects LLP · Hosakote, Bengaluru Rural · Plotted Development
7 of 211 plots booked · 65% developed · 59% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2027
- Ar Belle Vie Phase 1
S & S PROPERTIES and JMD Developers · Hosakote, Bengaluru Rural · Residential/Group Housing
9 of 222 homes booked · 10% built · 8% of the promised time used · Q1 2026-27 filing · completion promised 5 Feb 2029
- Arya’s Avadana
ARYAVARIDHI PROJECTS · Hosakote, Bengaluru Rural · Residential/Group Housing
9 of 64 homes booked · 31% built · 15% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Bhuvana Boulevard Phase 1
VSPR DEVELOPERS · Hosakote, Bengaluru Rural · Residential/Group Housing
1 of 28 homes booked · 11% built · 21% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Bhuvana Boulevard Phase 2
VSPR DEVELOPERS · Hosakote, Bengaluru Rural · Residential/Group Housing
4 of 28 homes booked · 10% built · 21% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Bold Aspire
Bold Developers · Hosakote, Bengaluru Rural · Residential/Group Housing
49 of 162 homes booked · 70% built · 78% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Brigade Citrine
Brigade Enterprises Ltd · Hosakote, Bengaluru Rural · Residential/Group Housing
404 of 420 homes booked · 38% built · 34% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2029
- Carpe Diem
VIJAYASRI VIJETHA INFRA PROJECTS · Hosakote, Bengaluru Rural · Plotted Development
10 of 125 plots booked · 75% developed · 43% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Daiwik Sayuri
DAIWIK SHELTERS PRIVATE LIMITED · Hosakote, Bengaluru Rural · Plotted Development
0 of 211 plots booked · 95% developed · 72% of the promised time used · Q1 2026-27 filing · completion promised 1 Dec 2026
- DR Elita
DR Infra · Hosakote, Bengaluru Rural · Plotted Development
0 of 74 plots booked · 85% developed · 22% of the promised time used · Q1 2026-27 filing · completion promised 31 Jan 2028
- DS Max SKY Fields
DS Max Properties Private Limited · Hosakote, Bengaluru Rural · Residential/Group Housing
239 of 870 homes booked · 31% built · 28% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2030
- DS Max SKY Samurai
DS-MAX PROPERTIES PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
162 of 285 homes booked · 98% built · 49% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- East Field
URBANEST REALTY · Hosakote, Bengaluru Rural · Residential/Group Housing
68 of 200 homes booked · 33% built · 31% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Eeshanya Aaroha
EESHANYA INFRA LLP · Hosakote, Bengaluru Rural · Residential/Group Housing
36 of 120 homes booked · 40% built · 29% of the promised time used · Q1 2026-27 filing · completion promised 31 May 2028
- Garuda Park View
GARUDA CONSTRUCTIONS · Hosakote, Bengaluru Rural · Residential/Group Housing
15 of 90 homes booked · 16% built · 13% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2029
- Godrej Parkshire
Godrej Properties Limited · Hosakote, Bengaluru Rural · Residential/Group Housing
594 of 1132 homes booked · 3% built · 9% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2030
- Godrej Woodland
Godrej Properties Ltd · Hosakote, Bengaluru Rural · Plotted Development
900 of 900 plots booked · 88% developed · 91% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Godrej Woodland Phase 2
Godrej Properties Limited · Hosakote, Bengaluru Rural · Plotted Development
125 of 125 plots booked · 88% developed · 88% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Green Park
SSV DEVELOPERS · Hosakote, Bengaluru Rural · Residential/Group Housing
45 of 208 homes booked · 20% built · 12% of the promised time used · Q1 2026-27 filing · completion promised 20 Nov 2029
- Irise
M/s. Upstate United · Hosakote, Bengaluru Rural · Plotted Development
0 of 166 plots booked · 80% developed · 20% of the promised time used · Q1 2026-27 filing · completion promised 15 Jan 2029
- Isha Hilife
ISHA CORP · Hosakote, Bengaluru Rural · Residential/Group Housing
131 of 199 homes booked · 95% built · 81% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- JB Vision
G Babu · Hosakote, Bengaluru Rural · Plotted Development
10 of 155 plots booked · 100% developed · 100% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2026
- JP Hibiscus
JPHC PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
31 of 76 homes booked · 53% built · 50% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- JP Iris Block-A
JP Housing Corporation · Hosakote, Bengaluru Rural · Residential/Group Housing
23 of 92 homes booked · 48% built · 21% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- JP Iris Block-B
JP Housing Corporation · Hosakote, Bengaluru Rural · Residential/Group Housing
28 of 88 homes booked · 36% built · 14% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- JP Jasmine
JPHC PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
4 of 66 homes booked · 32% built · 14% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- JP Lavender Block-A
JP Housing Corporation · Hosakote, Bengaluru Rural · Residential/Group Housing
30 of 76 homes booked · 71% built · 81% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- JP Lavender Block-B
JP Housing Corporation · Hosakote, Bengaluru Rural · Residential/Group Housing
9 of 24 homes booked · 67% built · 81% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- JR One East
JR Housing Developers Pvt Ltd · Hosakote, Bengaluru Rural · Plotted Development
21 of 177 plots booked · 95% developed · 39% of the promised time used · Q1 2026-27 filing · completion promised 30 Nov 2028
- KBR Prime
KBR HOMES INDIA PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
2 of 124 homes booked · 95% built · 39% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2029
- Kumari Nautilus
KUMARI INFRA HOMES PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
114 of 165 homes booked · 85% built · 66% of the promised time used · Q1 2026-27 filing · completion promised 12 Jan 2028
- Leafy Delight
LEAFY REALTY LLP · Hosakote, Bengaluru Rural · Residential/Group Housing
12 of 67 homes booked · 55% built · 32% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2028
- M1 Terra Alegria Phase 2
M1 HOUSING LLP · Hosakote, Bengaluru Rural · Plotted Development
223 of 224 plots booked · 100% developed · 100% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2026
- Mizar
NAGARJUNA STRUCTURAL CORPORATION PRIVATE LIMITED · Hosakote, Bengaluru Rural · Plotted Development
0 of 44 plots booked · 50% developed · 4% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Nexon Celestials
NEXON BUILDERS AND DEVELOPERS · Hosakote, Bengaluru Rural · Plotted Development
0 of 76 plots booked · 95% developed · 17% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Nexon Travenza
NEXON Developers · Hosakote, Bengaluru Rural · Plotted Development
2 of 36 plots booked · 45% developed · 10% of the promised time used · Q1 2026-27 filing · completion promised 25 Aug 2031
- Nexon Travenza
NEXON BUILDERS · Hosakote, Bengaluru Rural · Plotted Development
2 of 83 plots booked · 29% developed · 12% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2031
- One Residences At Sobha One World Ph1 W1 and 2
SOBHA LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
150 of 542 homes booked · 0% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 31 Jul 2032
- One Residences At Sobha One World Ph2 W3 and 4
SOBHA LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
0 of 530 homes booked · 0% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 30 Nov 2032
- One Residences At Sobha One World Ph3 W5 and 6
SOBHA LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
0 of 530 homes booked · 0% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2033
- One Residences At Sobha One World Ph4 W7 and 8
SOBHA LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
74 of 440 homes booked · 0% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2033
- One Residences At Sobha One World Ph5 W9,10,11
SOBHA LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
345 of 721 homes booked · 0% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 28 Feb 2033
- One Residences At Sobha One World Ph6 W12,13,14
SOBHA LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
315 of 721 homes booked · 0% built · 2% of the promised time used · Q1 2026-27 filing · completion promised 31 Aug 2032
- Ridhi Vivanta
M/S. RIDHI VIVANTA · Hosakote, Bengaluru Rural · Plotted Development
0 of 145 plots booked · 100% developed · 41% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Rings Avenue
VARASINDURI PROPERTIES · Hosakote, Bengaluru Rural · Residential/Group Housing
58 of 144 homes booked · 55% built · 31% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2029
- Riqueza Siri
Riqueza Estates Private Limited · Hosakote, Bengaluru Rural · Residential/Group Housing
59 of 128 homes booked · 87% built · 67% of the promised time used · Q1 2026-27 filing · completion promised 30 Nov 2027
- Riviera Uno
NIRVANA DEVELOPERS · Hosakote, Bengaluru Rural · Residential/Group Housing
109 of 137 homes booked · 60% built · 28% of the promised time used · Q1 2026-27 filing · completion promised 31 Jan 2030
- Saritha Santorini
Saritha Developers · Hosakote, Bengaluru Rural · Residential/Group Housing
0 of 1 homes booked · 15% built · 28% of the promised time used · Q1 2026-27 filing · completion promised 30 Apr 2029
- Shubha Nivas
M/S. JAGATI INFRA · Hosakote, Bengaluru Rural · Residential/Group Housing
39 of 72 homes booked · 97% built · 87% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Sidvin Serenity
SIDVIN URBAN DEVELOPERS · Hosakote, Bengaluru Rural · Plotted Development
70 of 165 plots booked · 32% developed · 29% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Silver Stream
ARK GLOBAL ESTATES · Hosakote, Bengaluru Rural · Plotted Development
0 of 74 plots booked · 100% developed · 11% of the promised time used · Q1 2026-27 filing · completion promised 12 Sept 2028
- Sisira Park
SREEHAN INFRACON (OPC) PRIVATE LIMITED · Hosakote, Bengaluru Rural · Plotted Development
0 of 78 plots booked · 15% developed · 4% of the promised time used · Q1 2026-27 filing · completion promised 22 Jan 2030
- SJ Park Ville
SJ CONSTRUCTIONS · Hosakote, Bengaluru Rural · Residential/Group Housing
6 of 118 homes booked · 9% built · 7% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- Sowparnika Euphoria In The East
SOWPARNIKA HOMES PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
1083 of 1102 homes booked · 50% built · 28% of the promised time used · Q1 2026-27 filing · completion promised 31 May 2031
- Sowparnika Indradhanush Phase II
SOWPARNIKA HOMES PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
357 of 360 homes booked · 98% built · 71% of the promised time used · Q1 2026-27 filing · completion promised 30 Nov 2027
- Sowparnika Rhythm of Rain
SOWPARNIKA HOMES PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
675 of 725 homes booked · 34% built · 20% of the promised time used · Q1 2026-27 filing · completion promised 15 Jan 2032
- Sowparnika Whispering Petals
SOWPARNIKA GREEN MEADOWS PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
698 of 762 homes booked · 18% built · 10% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2032
- Svanta
Akkruthi Livespaces LLP · Hosakote, Bengaluru Rural · Plotted Development
259 of 259 plots booked · 17% developed · 23% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Tapasya
Keisha Projects Private Limited · Hosakote, Bengaluru Rural · Plotted Development
0 of 80 plots booked · 36% developed · 25% of the promised time used · Q1 2026-27 filing · completion promised 30 Jul 2027
- Tattvam
Yellow Stone Developers · Hosakote, Bengaluru Rural · Plotted Development
12 of 240 plots booked · 70% developed · 52% of the promised time used · Q1 2026-27 filing · completion promised 30 May 2027
- The Berries for Birds by Sanjeevini Srushti
SANJEEVINI SRUSHTI PROPERTIES · Hosakote, Bengaluru Rural · Plotted Development
6 of 277 plots booked · 28% developed · 46% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2027
- Triaxis Splendour +
M s Triaxis Infra Projects · Hosakote, Bengaluru Rural · Residential/Group Housing
58 of 104 homes booked · 94% built · 91% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Trivik Signature
TRIVIK SIGNATURE · Hosakote, Bengaluru Rural · Residential/Group Housing
13 of 408 homes booked · 13% built · 6% of the promised time used · Q1 2026-27 filing · completion promised 26 Dec 2031
- United Green Woods
UNITED GREEN WOODS · Hosakote, Bengaluru Rural · Residential/Group Housing
183 of 282 homes booked · 54% built · 49% of the promised time used · Q1 2026-27 filing · completion promised 16 Mar 2028
- United Suvarna Homes
UNITED SUVARNA HOMES · Hosakote, Bengaluru Rural · Residential/Group Housing
0 of 156 homes booked · 25% built · 18% of the promised time used · Q1 2026-27 filing · completion promised 8 Sept 2029
- V.R Mega Township
VR VENTURES · Hosakote, Bengaluru Rural · Plotted Development
11 of 192 plots booked · 17% developed · 39% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- VR Dyavaiah Enclave
VR REALTY · Hosakote, Bengaluru Rural · Plotted Development
0 of 50 plots booked · 7% developed · 9% of the promised time used · Q1 2026-27 filing · completion promised 30 Jun 2028
- VR Royal Township
VR BUILDERS AND DEVELOPERS · Hosakote, Bengaluru Rural · Plotted Development
115 of 385 plots booked · 57% developed · 78% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- VR Sapphire
VR Builders And Developers · Hosakote, Bengaluru Rural · Residential/Group Housing
24 of 46 homes booked · 60% built · 78% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Whispers Of Bliss
VENKATESWARA CREATORS · Hosakote, Bengaluru Rural · Residential/Group Housing
1 of 12 homes booked · 60% built · 68% of the promised time used · Q1 2026-27 filing · completion promised 15 Dec 2026
- Adithya Homes Paradise Phase-4
ADITHYA HOMES · Hosakote, Bengaluru Rural · Plotted Development
16 of 86 plots booked · 100% developed · 76% of the promised time used · Q4 2025-26 filing · completion promised 22 Jun 2026
- Elements Of Nature Happy Hive
URBAN FIELDS REALTY LLP · Hosakote, Bengaluru Rural · Plotted Development
149 of 150 plots booked · 100% developed · 53% of the promised time used · Q4 2025-26 filing · completion promised 9 Aug 2027
- Sidvin Symphony
AVYANHP SHARAYU · Hosakote, Bengaluru Rural · Plotted Development
51 of 157 plots booked · 100% developed · 100% of the promised time used · Q4 2025-26 filing · completion promised 31 Mar 2026
- Bodhii Tree
VAISHNAVI RESIDENCES · Hosakote, Bengaluru Rural · Plotted Development
18 of 109 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 30 Dec 2025
- Gold Star Layout
A IQBAL KHAN · Hosakote, Bengaluru Rural · Plotted Development
0 of 138 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- JR Eastfields
JR HOUSING DEVELOPERS PVT LTD · Hosakote, Bengaluru Rural · Plotted Development
103 of 389 plots booked · 100% developed · 79% of the promised time used · Q3 2025-26 filing · completion promised 1 Aug 2026
- JR STRR Enclave
JR Housing Developers Pvt Ltd · Hosakote, Bengaluru Rural · Plotted Development
8 of 33 plots booked · 100% developed · 90% of the promised time used · Q3 2025-26 filing · completion promised 11 Apr 2026
- Mattania Serenity
MATTANIA INFRATECH PRIVATE LIMITED · Hosakote, Bengaluru Rural · Plotted Development
0 of 44 plots booked · 100% developed · 87% of the promised time used · Q3 2025-26 filing · completion promised 23 Feb 2026
- Mithila Splendor
SRI JAGATI PROPERTIES · Hosakote, Bengaluru Rural · Residential/Group Housing
87 of 164 homes booked · 90% built · 70% of the promised time used · Q3 2025-26 filing · completion promised 31 Oct 2026
- Orion Enclave
ORION REALTORS · Hosakote, Bengaluru Rural · Plotted Development
74 of 83 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 30 Dec 2025
- Provident Botanico
Provident Housing Limited · Hosakote, Bengaluru Rural · Residential/Group Housing
141 of 148 homes booked · 34% built · 39% of the promised time used · Q3 2025-26 filing · completion promised 30 Sept 2028
- Sapthagiri Sampadha
Sapthagiri Constructions · Hosakote, Bengaluru Rural · Residential/Group Housing
42 of 96 homes booked · 100% built · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
- Sowparnika Ashiyana Phase II
SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED · Hosakote, Bengaluru Rural · Residential/Group Housing
419 of 422 homes booked · 100% built · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
Doddaballapura · 16 projects
- 99D BY Santhusta
M/s. SANTHUSTA INFRACON PRIVATE LIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
15 of 99 plots booked · 72% developed · 30% of the promised time used · Q1 2026-27 filing · completion promised 31 Jul 2028
- Aamaya
SRK INFRA PROJECTS PRIVATE LIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
0 of 18 plots booked · 0% developed · 8% of the promised time used · Q1 2026-27 filing · completion promised 31 Jan 2029
- Aravya Estate
GODREJ TOWNSHIP DEVELOPMENT LIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
669 of 669 plots booked · 54% developed · 14% of the promised time used · Q1 2026-27 filing · completion promised 31 Oct 2030
- Century Bliss
Hebbal Properties Private Limited · Doddaballapura, Bengaluru Rural · Residential/Group Housing
29 of 272 homes booked · 3% built · 4% of the promised time used · Q1 2026-27 filing · completion promised 7 Apr 2031
- DS Max SKY Sisira
DS Max Properties Private Limited · Doddaballapura, Bengaluru Rural · Residential/Group Housing
252 of 870 homes booked · 42% built · 28% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2030
- KNS Candrill
KNS EQUITY ESTATES LLP · Doddaballapura, Bengaluru Rural · Plotted Development
350 of 452 plots booked · 92% developed · 38% of the promised time used · Q1 2026-27 filing · completion promised 15 Jun 2029
- Lagos
B&M HOMES · Doddaballapura, Bengaluru Rural · Plotted Development
231 of 298 plots booked · 66% developed · 61% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Make Borough
IRON KORE PRIVATE LIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
24 of 35 plots booked · 100% developed · 66% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2027
- Nexfield
SIDDHATVA DEVELOPERS PRIVATE LIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
0 of 142 plots booked · 91% developed · 34% of the promised time used · Q1 2026-27 filing · completion promised 25 Nov 2027
- Northwinds by Geown & Nivara
GEOWN CASPER ESTATES LLP & Nivara Group · Doddaballapura, Bengaluru Rural · Plotted Development
43 of 126 plots booked · 87% developed · 26% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Rewild Doddaballapura
Rewild Life LLP · Doddaballapura, Bengaluru Rural · Plotted Development
114 of 141 plots booked · 64% developed · 42% of the promised time used · Q1 2026-27 filing · completion promised 13 Jun 2029
- Shriram Pristine Estates
SPL HOUSING PROJECTS PRIVATE LIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
513 of 513 plots booked · 100% developed · 100% of the promised time used · Q1 2026-27 filing · completion promised 15 May 2026
- The Silver Lake Phase 1
HARINATHA REDDY · Doddaballapura, Bengaluru Rural · Plotted Development
101 of 101 plots booked · 97% developed · 48% of the promised time used · Q1 2026-27 filing · completion promised 30 Dec 2026
- Whispers of the Wind
Sree Holdings · Doddaballapura, Bengaluru Rural · Plotted Development
23 of 207 plots booked · 31% developed · 25% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2029
- The Earth
SRK INFRA PROJECTS PRIVATELIMITED · Doddaballapura, Bengaluru Rural · Plotted Development
328 of 440 plots booked · 98% developed · 94% of the promised time used · Q4 2025-26 filing · completion promised 31 May 2026
- KBL Enclave - Phase 2
L KUMAR · Doddaballapura, Bengaluru Rural · Plotted Development
26 of 77 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
Nelamangala · 11 projects
- Artemis Address Phase 2
INDIABUILD REAL ESTATES PVT LTD · Nelamangala, Bengaluru Rural · Plotted Development
70 of 145 plots booked · 75% developed · 42% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Artemis Arena
MYTHREYI ADDRESS LLP · Nelamangala, Bengaluru Rural · Plotted Development
37 of 81 plots booked · 92% developed · 72% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2026
- Arvind Lakeview
Arvind Builders · Nelamangala, Bengaluru Rural · Plotted Development
0 of 522 plots booked · 90% developed · 60% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Chartered Gulmohar
CHARTERED HOUSING PRIVATE LIMITED · Nelamangala, Bengaluru Rural · Plotted Development
45 of 168 plots booked · 5% developed · 14% of the promised time used · Q1 2026-27 filing · completion promised 30 Sept 2028
- FRK Sapphire
FRK REALTY AND INFRA · Nelamangala, Bengaluru Rural · Plotted Development
0 of 635 plots booked · 90% developed · 31% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2028
- Green Groves
SATTVA INFRASTRUCTURE INDIA PRIVATE LIMITED · Nelamangala, Bengaluru Rural · Plotted Development
606 of 735 plots booked · 100% developed · 91% of the promised time used · Q1 2026-27 filing · completion promised 17 Sept 2026
- KNS Samooha Phase - II
KNS VINTAGE INFRA PRIVATE LIMITED · Nelamangala, Bengaluru Rural · Plotted Development
0 of 589 plots booked · 40% developed · 21% of the promised time used · Q1 2026-27 filing · completion promised 22 Aug 2029
- KNS Samooha Phase I
KNS VINTAGE INFRA PRIVATE LIMITED · Nelamangala, Bengaluru Rural · Plotted Development
0 of 760 plots booked · 40% developed · 30% of the promised time used · Q1 2026-27 filing · completion promised 22 Aug 2029
- KNS Samooha Phase III
KNS CK PROJECTS LLP · Nelamangala, Bengaluru Rural · Plotted Development
0 of 1225 plots booked · 10% developed · 21% of the promised time used · Q1 2026-27 filing · completion promised 23 Aug 2029
- Vistara 1
ANANTHAM GRUHAM DEVELOPERS PRIVATE LIMITED · Nelamangala, Bengaluru Rural · Plotted Development
0 of 253 plots booked · 95% developed · 35% of the promised time used · Q1 2026-27 filing · completion promised 31 Dec 2027
- Artemis Address (In Association with Mythreyi)
INDIABUILD REAL ESTATES PVT LTD · Nelamangala, Bengaluru Rural · Plotted Development
313 of 401 plots booked · 100% developed · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025
Ramanagara · 1 project
- Rock Hills
FIDELIS RAMNAGARA · Ramanagara, Bengaluru Rural · Plotted Development
10 of 49 plots booked · 100% developed · 89% of the promised time used · Q3 2025-26 filing · completion promised 30 Sept 2026
Builders in Bengaluru Rural
- SOBHA LIMITED · 9
- ONE BANGALORE LUXURY PROJECTS LLP · 7
- BCV Developers Pvt Ltd · 5
- Brigade Enterprises Ltd · 5
- PRESTIGE ESTATES PROJECTS LTD · 5
- BIRLA ARNAA LLP · 4
- EMBASSY DEVELOPMENTS LIMITED · 4
- JP Housing Corporation · 4
- DS Max Properties Private Limited · 3
- Elite Estates · 3
- JR Housing Developers Pvt Ltd · 3
- Konig Homes · 3
- Sattva Resi Private Limited · 3
- SOWPARNIKA HOMES PRIVATE LIMITED · 3
- AXIS CAPSTONE REALTY LLP · 2
- Godrej Properties Limited · 2
- INDIABUILD REAL ESTATES PVT LTD · 2
- ISHTIKA VIBRANIUM DEVELOPERS LLP · 2
- JPHC PRIVATE LIMITED · 2
- KNS VINTAGE INFRA PRIVATE LIMITED · 2
- M S RAMAIAH VENTURES LLP · 2
- Manyata Developers Pvt Ltd · 2
- MERUSRI DEVELOPERS · 2
- MF FARMLANDS PRIVATE LIMITED · 2
- NAGARJUNA STRUCTURAL CORPORATION PRIVATE LIMITED · 2
- Puravankara Limited · 2
- SRK INFRA PROJECTS PRIVATE LIMITED · 2
- TRINAYANI REALTOR PRIVATE LIMITED · 2
- VR BUILDERS AND DEVELOPERS · 2
- VSPR DEVELOPERS · 2
Figures are as the builders filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them. Projects that upload their updates as documents are not listed.