GR Swara

Ranke Infra LLP · Anekal, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/308/PR/020625/007803

Homes booked

10 of 58

48 still available · Q1 2026-27 filing, filed 15 Jul 2026

Construction against the schedule

Built38%
Promised time used29%

Registered 2 Jun 2025 · completion promised 31 Jan 2029. Time used is measured to the end of the quarter filed.

Every filing

Q1 2026-2710 / 58 booked38% built
Q4 2025-262 / 58 booked33% built
Q3 2025-268 / 58 booked28% built