Anand
SHARAD SHRINIVAS PAI · Belagavi · Residential/Group Housing
RERA PRM/KA/RERA/1249/447/PR/260924/007074
Homes booked
2 of 7
5 still available · Q2 2026-27 filing, filed 15 Oct 2026
Construction against the schedule
Built40%
Promised time used62%
Registered 26 Sept 2024 · completion promised 31 Dec 2027. Time used is measured to the end of the quarter filed.
Every filing
| Q2 2026-27 | 2 / 7 booked | 40% built |
| Q1 2026-27 | 2 / 7 booked | 36% built |
| Q4 2025-26 | 3 / 7 booked | 35% built |
| Q3 2025-26 | 3 / 7 booked | 28% built |
Is this your project?
See how fast it is selling, what is likely to be left at completion, and how it compares with similar projects — and let buyers reading this page ask you directly.
Join as a builderOther projects in Belagavi
- Adarsh Homes · D & K Associates18/42 booked
- Ambica Orchid · M/S. ABHIJEET ARVIND JAWALKAR2/10 booked
- Audumbar Residency · M/s. Bramha Construction7/16 booked
- Avadhoot Chaya · SHRI DATTAAVADHOOT DEVELOPERS LLP11/22 booked
- Bliss Residency · Kirti Pramod Nerlekar0/12 booked
- De-Prudent · MANJUNATH B GARAG INFRACON PRIVATE LIMITED0/10 booked
Figures are as the builder filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them.