Upavan, Phase II

Ma Sarada Constructions · Anekal, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/308/PR/060324/006683

Homes booked

43 of 72

29 still available · Q1 2026-27 filing, filed 15 Jul 2026

Construction against the schedule

Built95%
Promised time used74%

Registered 6 Mar 2024 · completion promised 30 Apr 2027. Time used is measured to the end of the quarter filed.

Every filing

Q1 2026-2743 / 72 booked95% built
Q4 2025-2643 / 72 booked92% built
Q3 2025-2643 / 72 booked85% built