Ellegenza Phase II

Nambiar Builders Private Limited · Anekal, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/308/PR/161024/007147

Homes booked

62 of 206

144 still available · Q1 2026-27 filing, filed 14 Jul 2026

Construction against the schedule

Built23%
Promised time used34%

Registered 16 Oct 2024 · completion promised 30 Sept 2029. Time used is measured to the end of the quarter filed.

Every filing

Q1 2026-2762 / 206 booked23% built
Q4 2025-2650 / 206 booked20% built
Q3 2025-2640 / 206 booked17% built

Is this your project?

See how fast it is selling, what is likely to be left at completion, and how it compares with similar projects — and let buyers reading this page ask you directly.

Join as a builder

Other projects in Bengaluru Urban

Figures are as the builder filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them.