23 of 170

147 still available · Q1 2026-27 filing, filed 15 Jul 2026

Construction against the schedule

Built49%
Promised time used24%

Registered 19 May 2025 · completion promised 31 Dec 2029. Time used is measured to the end of the quarter filed.

Every filing

Q1 2026-2723 / 170 booked49% built
Q4 2025-2620 / 170 booked43% built
Q3 2025-2618 / 170 booked35% built