Aryav Windfields

Aryav Constructions · Bengaluru East, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/446/PR/101024/007144

Homes booked

52 of 97

45 still available · Q1 2026-27 filing, filed 14 Jul 2026

Construction against the schedule

Built56%
Promised time used53%

Registered 10 Oct 2024 · completion promised 31 Dec 2027. Time used is measured to the end of the quarter filed.

Every filing

Q1 2026-2752 / 97 booked56% built
Q4 2025-2651 / 97 booked48% built
Q3 2025-2651 / 97 booked34% built