Check another project

Maitree Vajra

MAITREE DEVELOPERS · Bengaluru East, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/446/PR/110526/008641

Homes booked

0 of 50

50 still available · Q1 2026-27 filing, filed 15 Jul 2026

Construction against the schedule

Built24%
Promised time used7%

Registered 11 May 2026 · completion promised 31 Mar 2028. Time used is measured to the end of the quarter filed.

Is this your project?

See how fast it is selling, what is likely to be left at completion, and how it compares with similar projects — and let buyers reading this page ask you directly.

Join as a builder

Other projects in Bengaluru Urban

Figures are as the builder filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them.

Maitree Vajra RERA status: 0 of 50 homes booked · KRealtyX