Baldota Summit

BALDOTA BUILDERS AND DEVELOPERS · Bengaluru East, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/446/PR/220426/008598

Homes booked

2 of 77

75 still available · Q2 2026-27 filing, filed 9 Oct 2026

Construction against the schedule

Built18%
Promised time used11%

Registered 22 Apr 2026 · completion promised 31 Mar 2030. Time used is measured to the end of the quarter filed.

Every filing

Q2 2026-272 / 77 booked18% built
Q1 2026-272 / 77 booked13% built