DSR The Courtyard

DSR INFRAPROJECTS · Bengaluru East, Bengaluru Urban · Residential/Group Housing

RERA PRM/KA/RERA/1251/446/PR/280324/006759

Homes booked

109 of 229

120 still available · Q1 2026-27 filing, filed 15 Jul 2026

Construction against the schedule

Built93%
Promised time used78%

Registered 28 Mar 2024 · completion promised 22 Feb 2027. Time used is measured to the end of the quarter filed.

Every filing

Q1 2026-27109 / 229 booked93% built
Q4 2025-2699 / 229 booked88% built
Q3 2025-2682 / 229 booked80% built

Is this your project?