Airlink Luxor

Narasingasa Reality · Hubballi, Dharwad · Residential/Group Housing

RERA PRM/KA/RERA/1259/479/PR/261125/008277

Homes booked

21 of 49

28 still available · Q2 2026-27 filing, filed 15 Oct 2026

Construction against the schedule

Built20%
Promised time used19%

Registered 26 Nov 2025 · completion promised 31 Mar 2030. Time used is measured to the end of the quarter filed.

Every filing

Q2 2026-2721 / 49 booked20% built
Q1 2026-2720 / 49 booked15% built
Q4 2025-2610 / 49 booked12% built
Q3 2025-260 / 49 booked7% built

Is this your project?

See how fast it is selling, what is likely to be left at completion, and how it compares with similar projects — and let buyers reading this page ask you directly.

Join as a builder

Other projects in Dharwad

Figures are as the builder filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them.