New projects in Dharwad

Every project in Dharwad that files its sales and construction with Karnataka RERA, as filed.

Brokers: this week’s stock sheet for Dharwad →

Booked so far

1042 of 2639

Across 56 projects, at each one's latest filing.

Booked in Q2 2026-27

71

By the 34 projects that filed both of the last two quarters; 21 of them booked none.

Hubballi · 37 projects

  • A M Golden Heights

    A M Associates · Hubballi, Dharwad · Mixed Development

    4 of 26 homes booked · 18% built · 21% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2029

  • Access Indraprastha

    ACCESS DEVELOPERS AND BUILDERS · Hubballi, Dharwad · Residential/Group Housing

    1 of 16 homes booked · 48% built · 12% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Airlink Luxor

    Narasingasa Reality · Hubballi, Dharwad · Residential/Group Housing

    21 of 49 homes booked · 20% built · 19% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Annapurna Aaroh

    Vighneshwara Constructions · Hubballi, Dharwad · Residential/Group Housing

    5 of 16 homes booked · 53% built · 20% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Biradar Heritage

    Mahesh Basanna · Hubballi, Dharwad · Residential/Group Housing

    4 of 16 homes booked · 86% built · 59% of the promised time used · Q2 2026-27 filing · completion promised 31 Aug 2027

  • Bric Gardens

    Atman Studio (Prop. Satya Dev Chigurupati) · Hubballi, Dharwad · Residential/Group Housing

    0 of 17 homes booked · 30% built · 1% of the promised time used · Q2 2026-27 filing · completion promised 31 Dec 2030

  • Concorde Northwoods

    Concorde Sylvan View · Hubballi, Dharwad · Plotted Development

    193 of 238 plots booked · 96% developed · 60% of the promised time used · Q2 2026-27 filing · completion promised 8 Feb 2028

  • Elfin Nebula Siddeshwara

    ELFIN INFRA BUILDERS PRIVATE LIMITED · Hubballi, Dharwad · Mixed Development

    35 of 123 homes booked · 42% built · 64% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2028

  • Heritage Park

    HERITAGE INFRASPACE · Hubballi, Dharwad · Mixed Development

    8 of 17 homes booked · 95% built · 20% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Infinity Urban Suites

    INFINITY PROJECTS · Hubballi, Dharwad · Residential/Group Housing

    1 of 12 homes booked · 93% built · 51% of the promised time used · Q2 2026-27 filing · completion promised 24 Sept 2028

  • Jewel Paradise

    Redbricks · Hubballi, Dharwad · Mixed Development

    0 of 37 homes booked · 0% built · 20% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • King's Court

    Bhoomi Developers · Hubballi, Dharwad · Mixed Development

    4 of 57 homes booked · 47% built · 10% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Madhuban Divinity

    Horizon Constructions · Hubballi, Dharwad · Residential/Group Housing

    12 of 16 homes booked · 45% built · 9% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Nandavan

    M/s REDBRICKS · Hubballi, Dharwad · Residential/Group Housing

    10 of 18 homes booked · 86% built · 46% of the promised time used · Q2 2026-27 filing · completion promised 31 Dec 2028

  • Navarna Heights

    Vinod K Patil · Hubballi, Dharwad · Residential/Group Housing

    0 of 16 homes booked · 81% built · 21% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2029

  • Niketan Emerald

    NIKETAN EMERALD · Hubballi, Dharwad · Residential/Group Housing

    5 of 36 homes booked · 45% built · 38% of the promised time used · Q2 2026-27 filing · completion promised 15 Mar 2029

  • Niketan Luxuria

    NIKETAN BUILDERS PVT LTD · Hubballi, Dharwad · Residential/Group Housing

    15 of 16 homes booked · 100% built · 67% of the promised time used · Q2 2026-27 filing · completion promised 30 Sept 2027

  • Panchaganga Layout

    PANCHAGANGA INVESTMENTS · Hubballi, Dharwad · Plotted Development

    26 of 95 plots booked · 59% developed · 70% of the promised time used · Q2 2026-27 filing · completion promised 6 Jan 2028

  • Ruby Towers

    M/S MWS TOWERS · Hubballi, Dharwad · Mixed Development

    23 of 94 homes booked · 19% built · 37% of the promised time used · Q2 2026-27 filing · completion promised 30 Sept 2028

  • Sai Prestige

    B S A Constructions · Hubballi, Dharwad · Residential/Group Housing

    19 of 24 homes booked · 82% built · 19% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2029

  • Shankaratna Heights

    MANJUNATH B GARAG INFRACON PRIVATE LIMITED · Hubballi, Dharwad · Mixed Development

    55 of 170 homes booked · 19% built · 14% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2030

  • Shashi Enclave

    Vision Builders And Developers · Hubballi, Dharwad · Residential/Group Housing

    15 of 26 homes booked · 68% built · 56% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2028

  • Shreya Serenity

    SHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED · Hubballi, Dharwad · Mixed Development

    36 of 142 homes booked · 26% built · 24% of the promised time used · Q2 2026-27 filing · completion promised 15 Jan 2031

  • Shriya Ghodke Plaza

    KARTHIK MALODE · Hubballi, Dharwad · Mixed Development

    5 of 31 homes booked · 23% built · 33% of the promised time used · Q2 2026-27 filing · completion promised 4 Jan 2029

  • Shriya Lake View

    SHRIYA ANURAJ PROPERTIES · Hubballi, Dharwad · Mixed Development

    37 of 174 homes booked · 26% built · 44% of the promised time used · Q2 2026-27 filing · completion promised 20 Dec 2029

  • Shriya Symphony Heights

    Shriya BDP Properties · Hubballi, Dharwad · Mixed Development

    17 of 119 homes booked · 6% built · 4% of the promised time used · Q2 2026-27 filing · completion promised 15 Mar 2031

  • Bilva Residency

    Mahesh Basanna · Hubballi, Dharwad · Residential/Group Housing

    5 of 12 homes booked · 100% built · 53% of the promised time used · Q1 2026-27 filing · completion promised 29 Aug 2027

  • Shree Guruji Kunj Layout

    C G Parivar Constructions · Hubballi, Dharwad · Plotted Development

    0 of 23 plots booked · 100% developed · 13% of the promised time used · Q1 2026-27 filing · completion promised 31 Mar 2029

  • Tranquil

    Silver Nest Realty · Hubballi, Dharwad · Residential/Group Housing

    4 of 8 homes booked · 95% built · 43% of the promised time used · Q1 2026-27 filing · completion promised 30 Dec 2027

  • Aum Laxmi Residency

    Aum Builders And Developers · Hubballi, Dharwad · Residential/Group Housing

    22 of 40 homes booked · 100% built · 54% of the promised time used · Q4 2025-26 filing · completion promised 5 May 2028

  • Aum Mangal

    Nikhil Developers · Hubballi, Dharwad · Residential/Group Housing

    53 of 60 homes booked · 100% built · 100% of the promised time used · Q4 2025-26 filing · completion promised 31 Mar 2026

  • Marvel Ecron

    MARVEL PROPERTIES PRIVATE LIMITED · Hubballi, Dharwad · Commercial

    189 of 238 homes booked · 100% built · 100% of the promised time used · Q4 2025-26 filing · completion promised 31 Jan 2026

  • Aum Shankara

    NIKHIL DEVELOPERS · Hubballi, Dharwad · Residential/Group Housing

    11 of 15 homes booked · 90% built · 100% of the promised time used · Q3 2025-26 filing · completion promised 15 Dec 2025

  • Aum Shree Balaji

    M/s Nikhil Developers · Hubballi, Dharwad · Residential/Group Housing

    3 of 15 homes booked · 80% built · 50% of the promised time used · Q3 2025-26 filing · completion promised 20 Dec 2026

  • Newland Park

    S & S Builders and Developers · Hubballi, Dharwad · Residential/Group Housing

    20 of 50 homes booked · 100% built · 100% of the promised time used · Q3 2025-26 filing · completion promised 31 Dec 2025

  • Shriya Shivshakti Avenue

    SHRIYA PROJECTS · Hubballi, Dharwad · Mixed Development

    12 of 20 homes booked · 100% built · 93% of the promised time used · Q3 2025-26 filing · completion promised 3 Mar 2026

  • Shriya Vedamrit

    SHRIYA CONSTRUCTIONS · Hubballi, Dharwad · Residential/Group Housing

    7 of 12 homes booked · 100% built · 85% of the promised time used · Q3 2025-26 filing · completion promised 27 Apr 2026

Dharwad · 16 projects

Hubballi City · 3 projects

  • Midmac Vista

    Midmac Developers Private Limited · Hubballi City, Dharwad · Residential/Group Housing

    0 of 24 homes booked · 34% built · 17% of the promised time used · Q2 2026-27 filing · completion promised 31 Mar 2029

  • Nandi Vihar

    Nandi Developers and Builders · Hubballi City, Dharwad · Residential/Group Housing

    0 of 28 homes booked · 4% built · 17% of the promised time used · Q2 2026-27 filing · completion promised 1 Nov 2028

  • S F Towers

    NEW HOMES REALITY · Hubballi City, Dharwad · Mixed Development

    35 of 162 homes booked · 18% built · 9% of the promised time used · Q2 2026-27 filing · completion promised 30 Jun 2031

Builders in Dharwad

Figures are as the builders filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them. Projects that upload their updates as documents are not listed.