Nandi Vihar

Nandi Developers and Builders · Hubballi City, Dharwad · Residential/Group Housing

RERA PRM/KA/RERA/1259/503/PR/240426/008600

Homes booked

0 of 28

28 still available · Q2 2026-27 filing, filed 14 Oct 2026

Construction against the schedule

Built4%
Promised time used17%

Registered 24 Apr 2026 · completion promised 1 Nov 2028. Time used is measured to the end of the quarter filed.

Every filing

Q2 2026-270 / 28 booked4% built
Q1 2026-270 / 28 booked8% built