Gajabarwadi Phase A
ALTAF ABDULHAMID ATTAR · Hukkeri, Belagavi · Plotted Development
RERA PRM/KA/RERA/1249/369/PR/081223/006463
Plots booked
19 of 40
21 still available · Q2 2026-27 filing, filed 13 Oct 2026
A plot counts as booked when the filing shows an agreement of sale or a sale deed for it.
Development against the schedule
Developed61%
Promised time used92%
Registered 8 Dec 2023 · completion promised 31 Dec 2026. Time used is measured to the end of the quarter filed.
Every filing
| Q2 2026-27 | 19 / 40 booked | 61% developed |
| Q1 2026-27 | 21 / 40 booked | 61% developed |
| Q4 2025-26 | 19 / 40 booked | 61% developed |
| Q3 2025-26 | 19 / 40 booked | 56% developed |
Is this your project?
See how fast it is selling, what is likely to be left at completion, and how it compares with similar projects — and let buyers reading this page ask you directly.
Join as a builderOther projects in Belagavi
- Adarsh Homes · D & K Associates18/42 booked
- Ambica Orchid · M/S. ABHIJEET ARVIND JAWALKAR2/10 booked
- Anand · SHARAD SHRINIVAS PAI2/7 booked
- Audumbar Residency · M/s. Bramha Construction7/16 booked
- Avadhoot Chaya · SHRI DATTAAVADHOOT DEVELOPERS LLP11/22 booked
- Bliss Residency · Kirti Pramod Nerlekar0/12 booked
Figures are as the builder filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them.