Homes booked

0 of 12

12 still available · Q2 2026-27 filing, filed 15 Oct 2026

Construction against the schedule

Built65%
Promised time used26%

Registered 1 Apr 2026 · completion promised 5 Mar 2028. Time used is measured to the end of the quarter filed.

Every filing

Q2 2026-270 / 12 booked65% built
Q1 2026-270 / 12 booked45% built