Check another project

Siri Hari Crest

SIRI BUILDERS AND DEVELOPERS · Belagavi · Residential/Group Housing

RERA PRM/KA/RERA/1249/447/PR/160726/008811

Homes booked

0 of 13

13 still available · Q2 2026-27 filing, filed 15 Oct 2026

Construction against the schedule

Built25%
Promised time used6%

Registered 16 Jul 2026 · completion promised 30 Sept 2029. Time used is measured to the end of the quarter filed.

Is this your project?

See how fast it is selling, what is likely to be left at completion, and how it compares with similar projects — and let buyers reading this page ask you directly.

Join as a builder

Other projects in Belagavi

Figures are as the builder filed them with Karnataka RERA, read from the public portal. KRealtyX does not verify them and adds nothing to them.

Siri Hari Crest RERA status: 0 of 13 homes booked · KRealtyX